ALPHA REPORT: TRACK TEAM

 
Alpha Burndown Screenshot.PNG

BURNDOWN CHART

 

Takeaways:

  • Tasks added throughout sprint
  • Off target by day four
  • Significant productivity variance between Mondays and rest of week
     
 

FINDINGS AND SOLUTIONS

 

ASSESSMENT: LACK OF AGILE EXPERIENCE

SEVERITY: HIGH

MANAGEMENT: COACHING

Coach team on purpose of scrum board: to see which single task a developer is working on at a time. Emphasize planned pad time is for estimation mistakes, not new tasks.

 

 

 

 

 

ASSESSMENT: ART TEAM UNDER-PERFORMING

SEVERITY: HIGH

MANAGEMENT: IMPROVE ACCOUNTABILITY

Connect track team artists to environment artists for greater accountability. Daily follow up with art lead.

 

ASSESSMENT: POOR PLANNING

SEVERITY: HIGH

MANAGEMENT: COACHING

Involve team in writing user stories. Correlate tasks with conditions of satisfaction.

IRL_Game Icon.png